When would it all happen?
If planning permission is granted, the Earls Court Project would be built in phases to minimise disruption to people who live in the area.

The map above shows our initial phasing plan. The dates below for each phase are only a guideline and may change.
Phase 1, Seagrave Road
Earliest start date - Q3 2012
Completing in phases from 2014 - 2018

Phase 2, Earls Court Village
Earliest start date - Q3 2012
Completion date - 2019

Phase 3, North End Village
Earliest start date - Q1 2015
Completion date - 2022

Phase 4, West Brompton Village
Earliest start date - Q2 2015
Completion date - 2023

Phase 5, Lost River Park
Earliest start date - Q4 2018
Completion date - 2025

Phase 6, North End Village North side
Earliest start date - Q4 2018
Completion date - 2027

Phase 7, West Kensington Village
Earliest start date - Q4 2023
Completion date - 2032

Tell us what you think
If you have any questions or comments about phasing, or any other part of the masterplan, please register, post a message in our forum and we’ll get back to you.