When would it happen?
Construction
We recognise that a key aspect of the successful management of the Seagrave Road development is the maintenance of good relations with neighbours. To achieve this, we will implement a programme of ongoing liaison, including:
* A dedicated Community Liaison Manager who will focus on engaging with the community to provide information and resolve any issues
* A dedicated phone number / hot line
* Regular monthly newsletters will be distributed around the neighbourhood with regular updates posted on our website
* Regular neighbourhood forums and exhibitions will be held to explain the proposed works
* Public notice boards will be established at site entrances
Phasing
We anticipate that the construction of the Seagrave Road development will take just over 5 years. We intend to start construction works after the Olympic Games in October 2012.
The development will be split into 4 construction phases:
* Phase 1a - September 2012 to summer 2015
* Phase 1b - September 2012 to winter 2014
* Phase 2 - summer 2014 to autumn 2016
* Phase 3 - autumn 2015 to winter 2017
* Phase 4 - summer 2017 to winter 2018